Taiwan Level B Interior Wiring Station 2 Simulator

STATION 2 · Q8

Station 2, Task 8: assembly of a Wh, varh, PF, V and A monitoring panel for a three-phase three-wire load (simulated high-voltage load with PTs and CTs)

This page covers the sequence of operation, the time limit and the materials of Station 2 (Task 8: Wh, varh, PF, V, A monitoring panel) of the Taiwan Level B interior wiring technician practical exam. On this site you can practice wiring, crimping and a test run in the browser following the circuit diagram and the arrangement drawing, with automatic grading against the assessment sheet.

The panel of Task 8: Wh, varh, PF, V, A monitoring panel with the reference solution wired: the control box, the enclosure door and the wires
The panel of Task 8: Wh, varh, PF, V, A monitoring panel (reference solution)

Sequence of operation (動作說明)

Assemble a monitoring panel for a three-phase three-wire 10 kVA load: two potential transformers (PT, V-V connection) and two through-type current transformers (CT) feed the watt-hour meter, the var-hour meter and the power factor meter, and the voltmeter and ammeter are connected through the voltmeter selector switch VS and the ammeter selector switch AS.

  1. 1
    Power on

    The watt-hour meter and var-hour meter turn forward.

  2. 2
    VS and AS at OFF

    The voltmeter and ammeter read zero.

  3. 3
    Switch VS and AS to each phase

    The voltmeter and ammeter read the voltage and current of that phase.

Workmanship rules

The potential transformer circuit uses 2 mm² red wire, the current transformer circuit 2 mm² black and the main circuit 8 mm² black; the number of turns through each CT is calculated to match the ammeter. The leads of VS and AS are unmarked, so identify them yourself with a multimeter. In this task every wire end a candidate makes needs a crimp terminal, and candidates also wire the U-shaped hinge loop between the enclosure body and the enclosure door (TB3 ↔ TB4).

Time limit and materials

Time limit: 90 min

Wire and crimp terminals issued to candidates

From the official list of materials issued to candidates; the test site gives more when you run out.

NameSpecificationQuantity
PVC-insulated wire600V, 2mm², red10 m
PVC-insulated wire600V, 2mm², black10 m
PVC-insulated wire600V, 8mm², black3 m
PVC-insulated wire600V, 5.5mm², green2 m
PVC-insulated wire600V, 2mm², green2 m
Crimp terminal5.5mm²-5, "O"12 pcs
Crimp terminal2mm²-5, "O"2 pcs
Crimp terminal2mm²-4, "Y"100 pcs
Crimp terminal5.5mm²-5, "Y"6 pcs
Crimp terminal8mm²-5, "Y"6 pcs
Devices installed at the test site
NameSpecificationQuantity
Molded-case circuit breaker3P, 220V, 50AF, 50AT, IC5kA1 pcs
AC voltmeterpanel-mount, coil 150V, scale 0-300V1 pcs
AC ammeterpanel-mount, AC 0-5A, scale 0-50A1 pcs
D-type fuse500V, 2A, with fuse base3 pcs
Voltmeter selector switch3φ3W 250VAC, 10A, with sealed enclosure1 pcs
Ammeter selector switch3φ3W 250VAC, 10A, with sealed enclosure1 pcs
Potential transformer1φ 220/110V, 100VA2 pcs
Current transformer50/5A 15VA2 pcs
Watt-hour meter3φ3W, 110V/5A1 pcs
Var-hour meter3φ3W, 110V/5A1 pcs
Power factor meter3φ3W, 110V/5A, balanced1 pcs
Terminal block3P, 600V, 50A2 pcs
Terminal block4P, 600V, 50A1 pcs
Terminal block6P, 600V, 20A3 pcs
Terminal block10P, 600V, 20A3 pcs
Terminal block20P, 600V, 20A2 pcs
Terminal block4P, 600V, 20A1 pcs
Main ground bar (接地極端子板)copper, 4P1 pcs
Equipment ground bar (接地線端子板)copper, 5P1 pcs
Three-phase load10kVA (candidate workstation equipment; LOAD in the circuit diagram)1 unit

Practicing this task here

New devices in Task 8: potential transformers PT (220/110V, two in V-V connection, + terminal first), through-type current transformers CT (50/5A, nameplate 2 turns: when wiring a main circuit wire, click the start → the CT window → choose the turns → the end; the side you start from is the K side. You can also select the wire later and change it in the "Wiring" tab), watt-hour meter, var-hour meter (terminals 1S P1 P3 3S 3L P2 1L), power factor meter, voltmeter and ammeter; device leads are pre-wired to the terminal blocks, and you wire between the terminal blocks; there is no door-crossing harness, so wire the U-shaped hinge loop (U 形過門線) TB3 ↔ TB4 yourself. VS and AS come in a sealed enclosure with unmarked leads: turn on the multimeter in the "Wiring" tab (no need to energize), click the knob to change position and measure TB9 and TB10 on the ohms range to identify them; you can also open the lead identification bench from the realistic mode card and label the leads once identified (not graded).

Open the simulator, pick this task and click terminals to wire it (normal mode routes wires automatically; in realistic mode you strip the wires, crimp the terminals and pull the wires into the wiring duct yourself). When you are done, switch to test run and operate it with power on, then submit for grading: the assessment sheet lists the demerits and where they are.

Full instructions: How to use

Practice this task →