Taiwan Level B Interior Wiring Station 2 Simulator

STATION 2 · Q2

Station 2, Task 2: motor forward/reverse control circuit with wye-delta starting and momentary power interruption protection

This page covers the sequence of operation, the time limit and the materials of Station 2 (Task 2: forward/reverse Y-△, momentary power interruption protection) of the Taiwan Level B interior wiring technician practical exam. On this site you can practice wiring, crimping and a test run in the browser following the circuit diagram and the arrangement drawing, with automatic grading against the assessment sheet.

The panel of Task 2: forward/reverse Y-△, momentary power interruption protection with the reference solution wired: the control box, the enclosure door and the wires
The panel of Task 2: forward/reverse Y-△, momentary power interruption protection (reference solution)

Sequence of operation (動作說明)

Adds momentary power interruption protection to the forward/reverse wye-delta starting of Task 1.

  1. 1
    Press FWD or REV

    The motor starts wye-delta as in Task 1, and the latching relay KR remembers the direction.

  2. 2
    △ run

    The off-delay time-delay relay TR2 operates.

  3. 3
    Power fails while running and returns within the TR2 setting

    The motor restarts automatically in the same direction with wye-delta starting.

  4. 4
    Power fails during wye starting, or for longer than the setting

    It does not restart.

  5. 5
    Press OFF

    TR3 cuts the control circuit for a while, so a normal stop never restarts by itself.

Workmanship rules

Indicator lamps: RL1 forward delta running, RL3 reverse delta running, RL2 wye starting, GL stopped; there is also a push-lock emergency stop button EMS. The whole main circuit is dashed and pre-wired at the test site; candidates wire the control circuit (1.25 mm² yellow) and the ground wire (8 mm² green). Wire ends at terminal blocks and ground bars, and ground wires, must have crimp terminals.

Time limit and materials

Time limit: 90 min

Wire and crimp terminals issued to candidates

From the official list of materials issued to candidates; the test site gives more when you run out.

NameSpecificationQuantity
PVC-insulated wire600V, 1.25mm², yellow1 roll
PVC-insulated wire600V, 8mm², green1 m
Crimp terminal1.25mm²-4, "Y"50 pcs
Crimp terminal8mm²-5, "O"6 pcs
Devices installed at the test site
NameSpecificationQuantity
Molded-case circuit breaker3P, 220V, 100AF, 75AT, IC10kA1 pcs
D-type fuse500V, 2A, with fuse base2 pcs
ContactorAC 220V 5.5kW(7.5HP), coil 220V 3P, auxiliary contacts 2a2b1 pcs
ContactorAC 220V 7.5kW(10HP), coil 220V 3P, auxiliary contacts 2a2b1 pcs
Reversing contactorAC 220V 11kW(15HP), coil 220V 3P, auxiliary contacts 2a2b, 2 units, reversing, mechanical interlock1 set
Thermal overload relay24A, adjustable, 3-heater1 pcs
Pushbutton switch (green)30mmφ, 600V, 1a1b2 pcs
Pushbutton switch (red)30mmφ, 600V, 1a1b1 pcs
Emergency stop pushbutton (red)30mmφ, 600V, 1a1b, push-lock, red, maintained1 pcs
Time-delay relayAC 220V, wye-delta type, 0-30sec time-delay contact 1c, with socket1 pcs
Time-delay relayAC 220V, 0-10sec, OFF Delay time-delay contact 1c, with socket2 pcs
Latching relayAC 220V, 5A, 2c, with socket1 pcs
Indicator light (red)AC 220V/15V, 18V bulb, 30mmφ3 pcs
Indicator light (green)AC 220V/15V, 18V bulb, 30mmφ1 pcs
Terminal block3P, 600V, 50A1 pcs
Terminal block8P, 600V, 30A1 pcs
Terminal block16P, 600V, 20A2 pcs
Main ground bar (接地極端子板)copper, 4P1 pcs
Equipment ground bar (接地線端子板)copper, 5P1 pcs
Three-phase induction motor15HP, 6 leads (candidate workstation equipment)1 unit

Practicing this task here

New devices in Task 2: TR2 and TR3 are off-delay relays (②⑦ supply, ⑧ common, ⑥ time-delay a, ⑤ time-delay b, ①c ③a ④b a second time-delay contact; they operate instantly when energized, reset only after the set time once de-energized, and keep timing during an outage); KR is a latching relay (11-pin: SET coil ②⑩, RESET coil ①⑪, contacts ③c ④a ⑤b, ⑨c ⑧a ⑦b; it remembers the direction through an outage); EMS is a push-lock emergency stop button that locks when pressed; click it again (twist) to release it. The test run can simulate an outage and a momentary power interruption.

Open the simulator, pick this task and click terminals to wire it (normal mode routes wires automatically; in realistic mode you strip the wires, crimp the terminals and pull the wires into the wiring duct yourself). When you are done, switch to test run and operate it with power on, then submit for grading: the assessment sheet lists the demerits and where they are.

Full instructions: How to use

Practice this task →