STATION 2 · Q2
Station 2, Task 2: motor forward/reverse control circuit with wye-delta starting and momentary power interruption protection
This page covers the sequence of operation, the time limit and the materials of Station 2 (Task 2: forward/reverse Y-△, momentary power interruption protection) of the Taiwan Level B interior wiring technician practical exam. On this site you can practice wiring, crimping and a test run in the browser following the circuit diagram and the arrangement drawing, with automatic grading against the assessment sheet.

Sequence of operation (動作說明)
Adds momentary power interruption protection to the forward/reverse wye-delta starting of Task 1.
- 1Press FWD or REV
The motor starts wye-delta as in Task 1, and the latching relay KR remembers the direction.
- 2△ run
The off-delay time-delay relay TR2 operates.
- 3Power fails while running and returns within the TR2 setting
The motor restarts automatically in the same direction with wye-delta starting.
- 4Power fails during wye starting, or for longer than the setting
It does not restart.
- 5Press OFF
TR3 cuts the control circuit for a while, so a normal stop never restarts by itself.
Workmanship rules
Indicator lamps: RL1 forward delta running, RL3 reverse delta running, RL2 wye starting, GL stopped; there is also a push-lock emergency stop button EMS. The whole main circuit is dashed and pre-wired at the test site; candidates wire the control circuit (1.25 mm² yellow) and the ground wire (8 mm² green). Wire ends at terminal blocks and ground bars, and ground wires, must have crimp terminals.
Time limit and materials
Time limit: 90 min
Wire and crimp terminals issued to candidates
From the official list of materials issued to candidates; the test site gives more when you run out.
| Name | Specification | Quantity |
|---|---|---|
| PVC-insulated wire | 600V, 1.25mm², yellow | 1 roll |
| PVC-insulated wire | 600V, 8mm², green | 1 m |
| Crimp terminal | 1.25mm²-4, "Y" | 50 pcs |
| Crimp terminal | 8mm²-5, "O" | 6 pcs |
Devices installed at the test site
| Name | Specification | Quantity |
|---|---|---|
| Molded-case circuit breaker | 3P, 220V, 100AF, 75AT, IC10kA | 1 pcs |
| D-type fuse | 500V, 2A, with fuse base | 2 pcs |
| Contactor | AC 220V 5.5kW(7.5HP), coil 220V 3P, auxiliary contacts 2a2b | 1 pcs |
| Contactor | AC 220V 7.5kW(10HP), coil 220V 3P, auxiliary contacts 2a2b | 1 pcs |
| Reversing contactor | AC 220V 11kW(15HP), coil 220V 3P, auxiliary contacts 2a2b, 2 units, reversing, mechanical interlock | 1 set |
| Thermal overload relay | 24A, adjustable, 3-heater | 1 pcs |
| Pushbutton switch (green) | 30mmφ, 600V, 1a1b | 2 pcs |
| Pushbutton switch (red) | 30mmφ, 600V, 1a1b | 1 pcs |
| Emergency stop pushbutton (red) | 30mmφ, 600V, 1a1b, push-lock, red, maintained | 1 pcs |
| Time-delay relay | AC 220V, wye-delta type, 0-30sec time-delay contact 1c, with socket | 1 pcs |
| Time-delay relay | AC 220V, 0-10sec, OFF Delay time-delay contact 1c, with socket | 2 pcs |
| Latching relay | AC 220V, 5A, 2c, with socket | 1 pcs |
| Indicator light (red) | AC 220V/15V, 18V bulb, 30mmφ | 3 pcs |
| Indicator light (green) | AC 220V/15V, 18V bulb, 30mmφ | 1 pcs |
| Terminal block | 3P, 600V, 50A | 1 pcs |
| Terminal block | 8P, 600V, 30A | 1 pcs |
| Terminal block | 16P, 600V, 20A | 2 pcs |
| Main ground bar (接地極端子板) | copper, 4P | 1 pcs |
| Equipment ground bar (接地線端子板) | copper, 5P | 1 pcs |
| Three-phase induction motor | 15HP, 6 leads (candidate workstation equipment) | 1 unit |
Practicing this task here
New devices in Task 2: TR2 and TR3 are off-delay relays (②⑦ supply, ⑧ common, ⑥ time-delay a, ⑤ time-delay b, ①c ③a ④b a second time-delay contact; they operate instantly when energized, reset only after the set time once de-energized, and keep timing during an outage); KR is a latching relay (11-pin: SET coil ②⑩, RESET coil ①⑪, contacts ③c ④a ⑤b, ⑨c ⑧a ⑦b; it remembers the direction through an outage); EMS is a push-lock emergency stop button that locks when pressed; click it again (twist) to release it. The test run can simulate an outage and a momentary power interruption.
Open the simulator, pick this task and click terminals to wire it (normal mode routes wires automatically; in realistic mode you strip the wires, crimp the terminals and pull the wires into the wiring duct yourself). When you are done, switch to test run and operate it with power on, then submit for grading: the assessment sheet lists the demerits and where they are.