STATION 2 · Q7
Station 2, Task 7: automatic transfer control circuit for normal supply and standby supply
This page covers the sequence of operation, the time limit and the materials of Station 2 (Task 7: normal/standby supply automatic transfer) of the Taiwan Level B interior wiring technician practical exam. On this site you can practice wiring, crimping and a test run in the browser following the circuit diagram and the arrangement drawing, with automatic grading against the assessment sheet.

Sequence of operation (動作說明)
- 1The normal supply (utility supply) comes on
TR2 times out and, through X2, the automatic transfer switch ATS transfers to the normal side; the W lamp lights.
- 2The normal supply fails for longer than the TR1 setting
Y2 lights to call for the generator.
- 3The standby supply (generator) comes on
TR4 times out and, through X3, ATS transfers to the standby side; the R lamp lights.
- 4The normal supply returns
ATS transfers back to the normal side, and Y2 goes out after TR3 times out.
Workmanship rules
Y1 lights while the ATS is transferring. The devices and wiring of the ATS panel are pre-wired at the test site; candidates wire the control circuit of the control box and its door (1.25 mm² yellow) and two ground wires (3.5 mm² green).
Time limit and materials
Time limit: 90 min
Wire and crimp terminals issued to candidates
From the official list of materials issued to candidates; the test site gives more when you run out.
| Name | Specification | Quantity |
|---|---|---|
| PVC-insulated wire | 600V, 1.25mm², yellow | 1 roll |
| PVC-insulated wire | 600V, 3.5mm², green | 1 m |
| Crimp terminal | 1.25mm²-4, "Y" | 50 pcs |
| Crimp terminal | 3.5mm²-5, "O" | 8 pcs |
Devices installed at the test site
| Name | Specification | Quantity |
|---|---|---|
| Molded-case circuit breaker | 3P, 220V, 50AF, 30AT, IC5kA | 2 pcs |
| D-type fuse | 500V, 2A, with fuse base | 5 pcs |
| Auxiliary relay | AC 220V, 5A, 2C, with socket | 4 pcs |
| Time-delay relay | AC 220V, 0-10sec, 1c, OFF DELAY, with socket | 1 pcs |
| Time-delay relay | AC 220V, 0-30sec, 1c, ON DELAY, with socket | 2 pcs |
| Time-delay relay | AC 220V 0-5min, 1c, ON DELAY, with socket | 1 pcs |
| Indicator light (white) | AC 220V/15V, 18V bulb, 30mmφ | 1 pcs |
| Indicator light (red) | AC 220V/15V, 18V bulb, 30mmφ | 1 pcs |
| Indicator light (yellow) | AC 220V/15V, 18V bulb, 30mmφ | 2 pcs |
| Terminal block | 3P, 600V, 30A | 2 pcs |
| Terminal block | 16P, 600V, 20A | 4 pcs |
| Automatic transfer switch | 3P, 600V, 100A, with electrical and mechanical interlocks and manual operating handle, 470mmW×220mmL×210mmH | 1 set |
| Main ground bar (接地極端子板) | copper, 4P | 2 pcs |
| Equipment ground bar (接地線端子板) | copper, 5P | 2 pcs |
Practicing this task here
New devices in Task 7: the ATS panel (right column) is fully pre-wired; its leads run via TB2 → control box TB1. When the ATS transfer motor TM is energized, it moves to the other side; on arrival, limit switches LSA (normal side) and LSB (standby side) operate and cut TM off (c-a closes, c-b opens). TR2, TR3 and TR4 are on-delay relays (same pinout as the off-delay relay: ②⑦ supply, ⑧ common, ⑥ time-delay a, ⑤ time-delay b; they time while energized, operate when the time is up and reset immediately when de-energized); TR1 is an off-delay relay. For the test run, operate NFB1 (normal supply) and NFB2 (standby supply = generator) as in work instructions (實作說明) item (5); Y2 lit means the generator should run; click the ATS manual operating handle to move it to the other side (while TM is de-energized).
Open the simulator, pick this task and click terminals to wire it (normal mode routes wires automatically; in realistic mode you strip the wires, crimp the terminals and pull the wires into the wiring duct yourself). When you are done, switch to test run and operate it with power on, then submit for grading: the assessment sheet lists the demerits and where they are.
Full instructions: How to use
Practice this task →