STATION 2 · Q3
Station 2, Task 3: two water pumps, manual/auto alternating operation control circuit
This page covers the sequence of operation, the time limit and the materials of Station 2 (Task 3: two water pumps, manual/auto alternating operation) of the Taiwan Level B interior wiring technician practical exam. On this site you can practice wiring, crimping and a test run in the browser following the circuit diagram and the arrangement drawing, with automatic grading against the assessment sheet.

Sequence of operation (動作說明)
Two water pumps fill the rooftop water tank, operated manually or automatically; on auto the two pumps alternate.
- 1Turn COS to manual (M)
ON1/OFF1 and ON2/OFF2 start and stop the two water pumps separately; the two are interlocked.
- 2Turn COS to auto (A) with the rooftop water tank low
The conductive level controller 61F-G senses the level and one pump runs.
- 3The water reaches E1
The pump stops and the ratchet relay MR switches once.
- 4The water is low again
The other pump runs.
- 5The supply tank is empty (float switch FS open)
No pump runs.
Workmanship rules
Indicator lamps: RL1 and RL2 pump running, GL1 tank full, GL2 both stopped; the buzzer sounds on TH-RY overload. The dashed lines TB1 → NFB, MC → TH-RY and terminal block → motor on the circuit diagram are pre-wired at the test site; candidates wire the main circuit from NFB to MC and from TH-RY to the terminal blocks (3.5 mm² black), the control circuit (1.25 mm² yellow) and the ground wires; E3 of the 61F-G must also be grounded.
Time limit and materials
Time limit: 90 min
Wire and crimp terminals issued to candidates
From the official list of materials issued to candidates; the test site gives more when you run out.
| Name | Specification | Quantity |
|---|---|---|
| PVC-insulated wire | 600V, 1.25mm², yellow | 1 roll |
| PVC-insulated wire | 600V, 3.5mm², black | 5 m |
| PVC-insulated wire | 600V, 2mm², green | 1.5 m |
| PVC-insulated wire | 600V, 3.5mm², green | 1 m |
| Crimp terminal | 1.25mm²-4, "Y" | 50 pcs |
| Crimp terminal | 3.5mm²-5, "Y" | 30 pcs |
| Crimp terminal | 2mm²-5, "O" | 4 pcs |
| Crimp terminal | 3.5mm²-5, "O" | 6 pcs |
Devices installed at the test site
| Name | Specification | Quantity |
|---|---|---|
| Molded-case circuit breaker | 3P, 220V, 50AF, 30AT, IC10kA | 1 pcs |
| D-type fuse | 500V, 2A, with fuse base | 2 pcs |
| Motor starter | AC 220V 3.7kW(5HP), coil 220V 3P, auxiliary contacts 2a2b, with 15A adjustable 2-heater thermal overload relay | 2 pcs |
| Thermal overload relay (starter-mounted) | 15A, adjustable, 2-heater | 2 pcs |
| Auxiliary relay | AC 220V, 5A, 2C, with socket | 1 pcs |
| Ratchet relay | AC 220V, 5A, 2C, with socket | 1 pcs |
| Pushbutton switch (green) | 30mmφ, 600V, 1a1b | 2 pcs |
| Pushbutton switch (red) | 30mmφ, 600V, 1a1b | 2 pcs |
| Selector switch | 30mmφ, 1a1b, 600V, maintained, 2-position | 1 pcs |
| Float switch | 110-220V 1HP, 1a1b, two-float | 1 pcs |
| Indicator light (red) | AC 220V/15V, 18V bulb, 30mmφ | 2 pcs |
| Indicator light (green) | AC 220V/15V, 18V bulb, 30mmφ | 2 pcs |
| Conductive level controller | AC 220V, single-circuit type, with electrode rods | 1 set |
| Electrode rod | E1, E2, E3 (supplied with the conductive level controller) | 1 set |
| Buzzer | AC 220V, 30mmφ, flush-mount | 1 pcs |
| Terminal block | 3P, 600V, 30A | 1 pcs |
| Terminal block | 4P, 600V, 30A | 2 pcs |
| Terminal block | 8P, 600V, 20A | 2 pcs |
| Terminal block | 16P, 600V, 20A | 2 pcs |
| Main ground bar (接地極端子板) | copper, 4P | 1 pcs |
| Equipment ground bar (接地線端子板) | copper, 5P | 1 pcs |
| Three-phase induction motor | 5HP, 3 leads (candidate workstation equipment) | 2 unit |
Practicing this task here
New devices in Task 3: X (auxiliary relay) and MR (ratchet relay: toggles on each energization and stays put when de-energized) are 8-pin 2c (②⑦ coil, ① common ③ a ④ b, ⑧ common ⑥ a ⑤ b); the 61F-G conductive level controller socket is pre-wired to TB7; it operates when the water reaches E1 (Tc-Ta closes) and resets only below E2; E3 needs its own ground (2 mm² green wire); click COS to switch M (manual) / A (auto). In the test run controls you can set the rooftop water tank level, water use and whether the supply tank has water (at the test site, E1 and E3 are shorted/opened by hand).
Open the simulator, pick this task and click terminals to wire it (normal mode routes wires automatically; in realistic mode you strip the wires, crimp the terminals and pull the wires into the wiring duct yourself). When you are done, switch to test run and operate it with power on, then submit for grading: the assessment sheet lists the demerits and where they are.
Full instructions: How to use
Practice this task →