Taiwan Level B Interior Wiring Station 2 Simulator

STATION 2 · Q4

Station 2, Task 4: sewage pump manual/auto alternating and abnormal-level parallel operation control circuit

This page covers the sequence of operation, the time limit and the materials of Station 2 (Task 4: sewage pumps, alternating + abnormal-level parallel operation) of the Taiwan Level B interior wiring technician practical exam. On this site you can practice wiring, crimping and a test run in the browser following the circuit diagram and the arrangement drawing, with automatic grading against the assessment sheet.

The panel of Task 4: sewage pumps, alternating + abnormal-level parallel operation with the reference solution wired: the control box, the enclosure door and the wires
The panel of Task 4: sewage pumps, alternating + abnormal-level parallel operation (reference solution)

Sequence of operation (動作說明)

  1. 1
    Turn COS to manual

    Pushbuttons start and stop the two sewage pumps separately.

  2. 2
    Turn COS to auto; the level rises to BS1

    The conductive level controller 61F-G2 runs one pump.

  3. 3
    The level falls

    The pump stops and the alternating relay (61F-APN2; a ratchet relay may be used instead) switches, so the other pump runs next time.

  4. 4
    The level keeps rising to BS2 (abnormal level)

    Both pumps run in parallel and the yellow lamp lights.

  5. 5
    The level falls below BS1

    Both pumps stop together.

Workmanship rules

Indicator lamps: RL1 and RL2 running, GL1 and GL2 stopped, YL abnormal level; the buzzer sounds on TH-RY overload. The supply comes in through NFB3 and branches to NFB1 and NFB2 (pre-wired at the test site), and the control supply is taken from the load side of NFB3; candidates wire the main circuit from NFB to MC and from TH-RY to the terminal blocks (3.5 mm² black), the control circuit (1.25 mm² yellow) and the ground wires.

Time limit and materials

Time limit: 90 min

Wire and crimp terminals issued to candidates

From the official list of materials issued to candidates; the test site gives more when you run out.

NameSpecificationQuantity
PVC-insulated wire600V, 1.25mm², yellow1 roll
PVC-insulated wire600V, 3.5mm², black3 m
PVC-insulated wire600V, 5.5mm², green0.5 m
PVC-insulated wire600V, 3.5mm², green1 m
PVC-insulated wire600V, 2mm², green1 m
Crimp terminal1.25mm²-4, "Y"50 pcs
Crimp terminal5.5mm²-5, "O"2 pcs
Crimp terminal3.5mm²-5, "O"6 pcs
Crimp terminal2mm²-5, "O"4 pcs
Crimp terminal3.5mm²-5, "Y"30 pcs
Devices installed at the test site
NameSpecificationQuantity
Molded-case circuit breaker3P, 220V, 50AF, 30AT, IC5kA2 pcs
Molded-case circuit breaker3P, 220V, 50AF, 40AT, IC5kA1 pcs
D-type fuse500V, 2A, with fuse base2 pcs
ContactorAC 220V 3.7kW(5HP), coil 220V 3P, auxiliary contacts 2a2b2 pcs
Auxiliary relayAC 220V, 5A, 2C, with socket1 pcs
Thermal overload relay (starter-mounted)15A, adjustable, 2-heater2 pcs
Pushbutton switch (green)30mmφ, 600V, 1a1b2 pcs
Pushbutton switch (red)30mmφ, 600V, 1a1b2 pcs
Selector switch30mmφ, 1a1b, 600V, maintained, 2-position1 pcs
Indicator light (green)AC 220V/15V, 18V bulb, 30mmφ2 pcs
Indicator light (red)AC 220V/15V, 18V bulb, 30mmφ2 pcs
Indicator light (yellow)AC 220V/15V, 18V bulb, 30mmφ1 pcs
BuzzerAC 220V, 30mmφ, flush-mount1 pcs
Terminal block3P, 600V, 30A1 pcs
Terminal block4P, 600V, 30A2 pcs
Terminal block6P, 600V, 20A1 pcs
Terminal block20P, 600V, 20A2 pcs
Terminal block12P, 600V, 20A1 pcs
Conductive level controllerAC 220V, two-circuit type, with electrode rods (61F-G2)1 set
Alternating relayAC 220V, 2c (61F-APN2; a ratchet relay may be substituted)1 set
Mercury float switch600V, 1a, tilt type2 set
Main ground bar (接地極端子板)copper, 4P1 pcs
Equipment ground bar (接地線端子板)copper, 5P1 pcs
Three-phase induction motor5HP, 3 leads (candidate workstation equipment)2 unit

Practicing this task here

New devices in Task 4: 61F-G2 two-circuit type conductive level controller (socket pre-wired to the vertical TB5 on the right; you wire the right column of TB5; relay No. 1 follows E1, relay No. 2 follows E4), 61F-APN2 alternating relay (8-pin, alternates the two pumps), and the sewage pit mercury float switches BS1 and BS2 (tilted up: closed, hanging down: open; leads pre-wired to TB7). Power enters NFB3; NFB1–3 can be switched individually on the panel; in the test run controls you can set the sewage pit level and sewage inflow (at the test site, the float angle is changed by hand).

Open the simulator, pick this task and click terminals to wire it (normal mode routes wires automatically; in realistic mode you strip the wires, crimp the terminals and pull the wires into the wiring duct yourself). When you are done, switch to test run and operate it with power on, then submit for grading: the assessment sheet lists the demerits and where they are.

Full instructions: How to use

Practice this task →